Rimrock Pipeline is 67.57 miles of 12″ and 16″ pipe designed to carry Coal Bed Methane gas with delivery points into Thunder Creek and WBI pipelines located in Campbell County, Wyoming.  The system can operate up to 1440 psig and was constructed in 2002.  Initial construction included four receipt meters and one delivery meter station and was completed with full pigging facilities.

Location: Campbell, Sheridan and Johnson Counties, Wyoming

Pipe: 39.43 miles of 12″ steel  and 28.14 miles of 16″ steel

Transporting: Coal Bed Methane Natural Gas

Design Engineer: PACE Engineering

Construction: Welded Construction

Radiographic Inspection: Mid American